Project 3 Quadrum, Vilnius LT 2021

In 2021, june – august electrophysical measurements of the eastern and northern hull and parking lot were taken:

1.Checking the insulation of cables and installations with a voltage of up to 1000 V.

2.Checking the circuit from the grounding (inlet bus) to the grounded (inlet) elements.

3.Checking lightning protection.

 

Client: KIWA Inspecta UAB

 

 

In 2023, october – december electrophysical measurements of the eastern, northern and southern hull and parking lot were taken:

1.Checking the insulation of cables and installations with a voltage of up to 1000 V.

2.Checking the circuit from the grounding (inlet bus) to the grounded (inlet) elements.

 

Client: City Servise Engineering